Gas_10 / Gas Interconnector Serbia - Croatia
Brief project description
Connecting the Croatian gas transmission system to the Serbian gas transmission system on the route Slobodnica - Sotin (Croatia) - Bačko Novo Selo (Serbia). First phase would be Negoslavci-Sotin-Bačko Novo Selo plus the pipeline Osijek-Vukovar. The project is a new interconnection, new entry point and transmission route for the needs of Serbia. The project will enhance the security of supply and the diversification of supply route for Serbia. It will furthermore enable Serbia to access the Croatian UGS and LNG terminal and enable supply of gas from Austria, Slovenia and Italy via the Croatian gas transmission system.
-
Basic project data
Descriptions Serbia Croatia Project promoter company/Organization full name Public Enterprise Srbijagas Novi Sad
Plinacro D.o.o. Shareholders of the project promoter company
Government of Serbia / TSO Transportgas Srbija 100% Government of Croatia Project name
Gas Interconnector Serbia-Croatia
Gas Interconnector Serbia-Croatia Project PECI or PMI
PMI PMI Project Code on the current (2020) PECI/PMI list
Gas_10 Gas_10 Project Name on the current (2020) PECI/PMI list
Gas Interconnector Serbia-Croatia (Phase I) Gas Interconnector Serbia-Croatia (Phase I) Project Code on the current (2019) EU PCI list n/a n/a Project Name on the current (2019) EU PCI list n/a n/a Project final investment decision status Non-FID Non-FID Project Name in the ENTSOG TYNDP 2020 Submission Interconnection Croatia/Serbia (Slobdnica-Sotin-Bačko Novo Selo) Interconnection Croatia/Serbia (Slobdnica-Sotin-Bačko Novo Selo) Project Code in the ENTSO(G/E) TYNDP 2020 Submission TRA-A-070 TRA-A-070 Project Name in National NDP /Infrastructure Plan Gas Interconnector Serbia-Croatia Section on the Serbian territory (Gospođinci - Bačko Novo Selo) Phase 1: Osijek-Vukovar; Sotin-Bačko Novo Selo;
Phase 2: Slobodnica-SotinProject Code in National NDP /Infrastructure Plan 7.3.3
Phase 1: 1.33; 1.21;
Phase 2: 1.20National NDP / Infrastructure plan publication year 2020 2020 National NDP/infrastructure plan publication website Transportgas Srbija development plan gas pipeline system for 2020-2029
Plinacro Ten-year gas transportation development plan of the Republic of Croatia 2021 - 2030
Project website according to Article 9(7) of Regulation (EU) 347/2013 Project Website Name/website of the designated competent authority in the country Ministry of Economy and Sustainable Development - Directorate of Energy Address of the designated competent authority in the country Radnička cesta 80, 10000 Zagreb -
Project details - technical information
Start point in country (Town/Interconnection Point)
Serbia section Bačko Novo Selo (HR-SR Border) (DN 600) Croatia section Phase 1: Osijek (26km) (DN 800);
Phase 2: Slobodnica (87km) (DN800)End point in country (Town/Interconnection Point) Serbia section Gospođinci (95km) (DN 600) Croatia section
Sotin (HR-SR Border) (DN 800) Pipeline capacity at border point Serbia Croatia X --> Exit (GWh/d) 32,8
Phase 1: 54,34;
Phase 2: 185,66X<-- Entry (GWh/d) 32,8 Phase 1: 42,11;
Phase 2: 197,89Compressor station location and capacity (MW) Serbia Croatia Name of the compressor station -
Project Implementation Plan Article 5(1)
Project Pre-feasibility Assessment Serbia Croatia Start: End: 2009 Start: 2009 End: 2017 Details - Explanation Percentage Done (%) 100% 100% Feasibility Assessment, ESIA/EIA and Design Studies Serbia Croatia Start: 2010 End: 2025 Start: 2014 End:2022 Details - Explanation ESIA done in 2010; Technical Feasibility Study in 2015 Technical Feasibility Study and ESIA by 2021; Economic Feasibility-CBA by 2022; Percentage Done (%) 20% 50% FEED/Main Design Serbia Croatia Start: 2024 End: 2025 Start: End: 2022 Details - Explanation Percentage Done (%) 0% 10% Market Survey - Open Season/Capacity Auction Serbia Croatia Start: End: 2024 Start: End: 2022 Details - Explanation First phase Percentage Done (%) 0% 0% Permitting Serbia Croatia Start: 2025 End: 2026 Start: End: 2023 Details - Explanation Percentage Done (%) 0% 20% Regulatory/Authority Approval of the project Serbia Croatia 2026 2017 Details - Explanation Final Investment Decision taken Serbia Croatia 2025 2023 Details - Explanation For the first phase Tendering Serbia Croatia Start: 2025 End: 2026 Start: End: 2023 Details - Explanation Percentage Done (%) 0% 0% Construction Serbia Croatia Start: 2026 End: 2028 Start: 2023 End: 2024 Details - Explanation Commissioning Serbia Croatia 2028 2024 Details - Explanation -
Project Annual Report Article 5(4)
Project evolution since 2013 Serbia Croatia Evolution driver description Delayed
Delayed Explanation Mitigation measures to ensure project schedule Project implementation actions conducted since 2016 Serbia Croatia Project development Permit Granting Consultation procedures Construction Commissioning -
Project CAPEX and financing information
CAPEX Information Serbia Croatia 2024 3 mEUR
20 mEUR
2025 2 mEUR 13 mEUR 2026
10 mEUR 40 mEUR 2027
25 mEUR 22,6 mEUR 2028 20 mEUR 0 mEUR Project CAPEX SUM
155,6 mEUR
Project CAPEX certainty (+/-%)
25% 25% Has the project CAPEX estimate changed since PECI/PMI submission Financing Information Serbia Croatia Applied for IFI Financing (yes/no) no
no
Granted (yes/no) no no Which institution and in what is the amount (mEUR)
When Applied for Grants from IPA/NIF (yes/no) no no Granted (yes/no) no no When What is the amount (mEUR) -
Additional project information
International Cooperation - International Agreement(s) signed Serbia Croatia When Signatories of the Agreement Short description Foreseen Regulatory Regime - Third Party Access Serbia Croatia Regulated Third Party Access X X Negotiated Third Party Access Exempted from Third Party Access capacity and duration (% of total and MW) Foreseen Tariff Regime Barriers to Project Implementation Serbia Croatia Regulatory Framework no no Permit Granting no no Financing no no Political no no Market no no Which incentives would support the realization of the project Final remarks, other