Kosovo*
Membership
-
Overall implementation performance
Overall implementation performance 2023
CLUSTER INDICATORS 2023 HIGHLIGHTS AND NEXT STEPS Markets and integration Opening of the day-ahead electricity market and its coupling with Albania is delayed. Kosovo* should proceed with the market coupling of Albania – Kosovo*, as well as with the adoption of the laws transposing the Electricity Integration Package. Decarbonising the energy sector During the reporting period, Kosovo* submitted to the Secretariat its draft NECP and launched its inaugural solar PV auctions. Kosovo* should adopt the long-term building renovation strategy and adopt of the Renewable Energy Law in line with the acquis. Ensuring energy security Significant unintentional deviations of the control area of Kosovo* and delayed payment for the costs incurred continue to represent a risk to the operational security in the synchronous area. The Law on Security of Networks and Information systems was adopted in February 2023. Kosovo* should transpose Regulation (EU) 2019/941 on Risk-preparedness in the Electricity Sector and start its implementation with the designation of a competent authority. Improving the environment The implementation status in the area of environment remains at a low level. The long-standing breach of non-compliance with the National Emission Reduction Plan ceilings remains unaddressed. Emission abatement measures must be taken immediately to address this. Performance of authorities By approving a set of rules governing the power exchange operation and appointing the NEMO, ERO created one of the prerequisites for further market integration in line with the Electricity Integration Package. The State Aid Commission remains inoperational due to the failure to appoint its members. The establishment of an operational State aid authority constitutes a priority. status: November 2023
source: compiled by the Energy Community Secretariat -
Dispute settlement cases
Dispute settlement cases
By end of the reporting period, Kosovo* had one dispute settlement case.
Procedures under Article 91 Energy CommunityTreaty where the procedure has been closed with the adoption of a Ministerial Council decision, but the breach has not been rectified yet. ECS-5/22 Environment status: November 2023
source: compiled by the Energy Community SecretariatSecurity of supply
Implementation indicators
-
Primary fuel mix and available energy
2021 Fuel mix in primary production of energy (in ktoe)
status: November 2023
source: EUROSTAT
2021 Gross available energy per product (in ktoe)
status: November 2023
source: EUROSTAT
-
Primary supply of electricity
Fuel mix and primary supply of electricity
* export [-]; negative value
status: November 2023
source: Ministry of Economy, compiled by the Energy Community Secretariat
-
Implementation by market indicators
Implementation by electricity market indicators
November 2023
source: compiled by the Energy Community Secretariat
-
Average annual prices
Average annual prices of electricity for end users per component
source: EUROSTAT
source: EUROSTAT
Implementation by security of supply indicators
* not applicable
status: November 2023
source: compiled by the Energy Community Secretariat
Decarbonising the energy sector
-
Implementation by decarbonisation indicators
Implementation by governance indicators
Implementation by renewable energy indicators
Implementation by energy efficiency indicators
November 2023
source: compiled by the Energy Community Secretariat
-
2030 renewable energy targets and capacities
Targets for share of energy from renewable sources
Contracting Party 2005 Share of energy from renewable sources 2020 Target for share of energy from renewable sources 2030 Target for share of energy from renewable sources Kosovo* 18,9% 25% 32,0% source: Decision 2022/02/MC-EnC on incorporating Clean Energy Package into Energy Community acquis
2022 Total capacities of renewable energy (MW)
status: November 2023
source: Ministry of Economy
-
2030 energy efficiency targets, energy consumption and trends
2030 Primary and Final Energy Consumption Targets
Contracting Party 2020 primary energy consumption (PEC) 2020 final energy consumption
(FEC)2030 primary energy consumption (PEC) 2030 final energy consumption
(FEC)Kosovo* 4,70 Mtoe 4,25 Mtoe 2,70 Mtoe 1,80 Mtoe source: Decision 2022/02/MC-EnC on incorporating Clean Energy Package into Energy Community acquis
2021 Primary Energy Consumption (PEC) and Trends
2021 Final Energy Consumption (FEC) and Trends
Energy intensity, 2021 value and trends: 0,46 ktoe/mil EUR, ↓ -2,3%
status: November 2023
source: EUROSTAT 2023 data, NECP and 2022 Ministerial Council Decision
-
Implementation by environment indicators
Implementation by environment indicators
status: November 2023
source: compiled by the Energy Community Secretariat
-
LCPD implementation
Installations Under the Large Combustion Plants Directive
Type of plants Number on plants of plants falling under the LCPD 5 of which opted out plants 0 of which plants falling under the NERP 5 source: compiled by the Energy Community Secretariat
2022 emissions versus NERP ceilings
source: compiled by the Energy Community Secretariat