EL_01d / Transbalkan Corridor: OHL Pljevlja (ME) - Lastva (ME)
Brief project description
- Lot 1 SS Lastva: construction of 400/110/35 kV Lastva Substation and extension of the existing 400/220/110 kV Pljevlja 2 Substation;
- Lot 2 OHL Lastva Čevo: construction of the double circuit line 2 x 400 kV Lastva Trebinje and Lastva Pljevlja (section Lastva Čevo), and the single circuit line 400 kV Lastva Podgorica (section Lastva Čevo);
- Lot 3 OHL Čevo Pljevlja: construction of the 400 kV Lastva Pljevlja line (section Čevo Pljevlja), which is partly double circuit.
-
Basic project data
Descriptions Montenegro Project promoter company/Organization full name Crnogorski Elektroprenosni Sistem AD (CGES)
Shareholders of the project promoter company
TERNA, AD Elektromreza Srbije… Project name
400 kV OHL Pljevlja (ME) - Lastva (ME)
Project PECI or PMI
PECI Project Code on the current (2018) PECI/PMI list
El_3 Project Name on the current (2018) PECI/PMI list
400 kV OHL Pljevlja (ME) - Lastva (ME) Project Code on the current (2017) EU PCI list no Project Name on the current (2017) EU PCI list n/a Project final investment decision status FID Project Name in the ENTSO(G/E) TYNDP 2018 Submission CSE8 Transbalkan Corridor Project Code in the ENTSO(G/E) TYNDP 2018 Submission No code yet, TYNDP2014 reference code 146 Project Name in National NDP /Infrastructure Plan Construction of the SS Lastva, Construction of the 400 kV OHL Lastva-Čevo and Construction of 400 kV OHL Čevo-Pljevlja Project Code in National NDP /Infrastructure Plan IPI007, IPI006a and IPI006b
National NDP / Infrastructure plan publication year 2011-2019 National NDP/infrastructure plan publication website CGES Project website according to Article 9(7) of Regulation (EU) 347/2013 Trans-Balkan corridor section Montenegro, CGES website
Name/website of the designated competent authority in the country Ministry of Economy Address of the designated competent authority in the country Rimski trg 46, Podgorica, Montenegro
-
Project details - technical information
Start point in country
SS Pljevlja End point in country SS Lastva Technical information Element type line
Investment type
new Line circuit type double / single circuit Voltage level value [kV] 400 Capacity [MW] 1100 Line length [km] 220 Line current type AC Line structure type overhead line -
Project Implementation Plan Article 5(1)
Project Pre-feasibility Assessment Montenegro Start: End: Details - Explanation There is no pre-feasibility for this project Percentage Done (%) Feasibility Assessment, ESIA/EIA and Design Studies Montenegro Start: 2010, April End: 2011, December Details - Explanation This Feasibility Study has demonstrated that the proposed connection is technically feasible and economically viable. Percentage Done (%) 100% FEED/Main Design Montenegro Start: 2014, April End: 2016, March Details - Explanation Main design for all lots obtained Percentage Done (%) 100% Market Survey - Open Season/Capacity Auction Montenegro Start: 2010, April End: 2011, December Details - Explanation Market analysis were carried out in scope of Feasibility Study Percentage Done (%) Permitting Montenegro Start: 2014, June End: Details - Explanation Construction permits obtained for all lots (SS Lastva, OHL Lastva-Čevo and OHL Čevo-Pljevlja), Process for obtaining Operation (Usage) permits for SS Lastva and OHL Lastva-Čevo is in progress Percentage Done (%) 70% Regulatory/Authority Approval of the project Montenegro 2011-2019 Details - Explanation Approval of Energy Regulatory Agency obtained through submission of CGES Investment Plans, in the period 2011-2019 Final Investment Decision taken Montenegro 2011, January Details - Explanation Final decision taken in January 2011 by signing the Project Coordination Agreement between CGES and Terna Tendering Montenegro Start: 2012, January End: 2014, November Details - Explanation All tendering processes (for Consultant and Contractors for all three lots) in line with the EBRD PPR finished. Percentage Done (%) 100% Construction Montenegro Start: 2014, July End: Details - Explanation Construction works in SS Lastva finished, OHL Lastva-Čevo construction works are in final stage while works on OHL Čevo-Pljevlja are 62% completed Commissioning Montenegro 2021, December Details - Explanation Commissioning of SS Lastva completed, while commissioning of OHL Lastva-Cevo is under preparation. -
Project Annual Report Article 5(4)
Project evolution since 2013 Montenegro Evolution driver description Rescheduled
Explanation Problems with expropriation process, Contractors design and execution on site Mitigation measures to ensure project schedule Coordination Committee has been formed by the Government of Montenegro consisting of key ministers and representatives of competent authorities with a task to address all pending issues related to the implementation of the project Project implementation actions conducted since 2016 Montenegro Project development Project is under construction
Permit Granting Construction permits obtained for all segments of the Project Consultation procedures In the line with EBRD procedure Construction Construction phase for SS Lastva finished-TOC issued, Construction of OHL Lastva-Cevo is in final stage, OHL Cevo-Pljevlja 62% finished Commissioning Commissioning of SS Lastva completed, while commissioning of OHL Lastva-Cevo is under preparation. -
Project CAPEX and financing information
CAPEX Information Montenegro Project CAPEX - total (mEUR) 127,122 mEUR
up to 2018 89,7 mEUR 2019
9,9 mEUR 2020
3,8 mEUR after 2020
2,6 mEUR Project CAPEX certainty (+/-%)
10% Has the project CAPEX estimate changed since PECI/PMI submission no Financing Information Montenegro Applied for IFI Financing (yes/no) yes
Granted (yes/no) yes Which institution and in what is the amount (mEUR)
EBRD-60 mEUR, kfw-25 mEUR grant funds When 2013, May Applied for Grants from IPA/NIF (yes/no) yes Granted (yes/no) yes When What is the amount (mEUR) A-MON-02FS- Feasibility Study 400 kV OHL Lastva-Pljevlja (0.65 mEUR) -
Additional project information
International Cooperation - International Agreement(s) signed Montenegro When July, 2017 Signatories of the Agreement State of Montenegro and Republic of Italy Short description Agreement concerning construction and operation of the interconnection between transmission systems of Montenegro and Italy and on implementation of strategic partnership Foreseen Regulatory Regime - Third Party Access Montenegro Regulated Third Party Access yes Negotiated Third Party Access n/a Exempted from Third Party Access capacity and duration (% of total and MW) n/a Barriers to Project Implementation Montenegro Regulatory Framework no Permit Granting no Financing no Political no Market no Which incentives would support the realization of the project Final remarks, other