Brief project description
Upgrade of the transmission network in western Serbia to 400 kV between S/s Obrenovac and S/s Bajina Basta, which implies a new 2x400 kV transmission line S/s Obrenovac – S/s Bajina Basta, reconstruction of existing S/s Obrenovac and upgrade of SS Bajina Basta to 400 kV level accounts for one of the four first phase Transbalkan corridor infrastructure investment items, due to be completed by 2026.
Transbalkan corridor - Phase I, consists of the following Sections - infrastructure investment items:
• I 2x400 kV overhead line (OHL) between SS Pancevo 2 and SS Resita (Romania)
• II 400 kV OHL SS Kragujevac 2 – SS Kraljevo 3, with voltage level upgrade in SS Kraljevo 3 at 400 kV voltage level
• III Upgrade of transmission network in Western Serbia at 400 kV voltage level between SS Obrenovac and SS Bajina Basta, which implies new double 400 kV OHL SS Obrenovac – SS Bajina Basta, reconstruction of existing SS Obrenovac and upgrade of SS Bajina Basta to 400 kV level
• IV 2x400 kV interconnection between SS Bajina Basta, SS Visegrad (Bosnia and Herzegovina) and SS Pljevlja (Montenegro).
Implementation of this project will build up a strong electricity transmission corridor between east and west Europe with the following main features:
• Transbalkan corridor represents a project which goal is strengthening of the important regional and panEuropean energy paths in directions from the northeast to the southwest and from east to west.
• Realization of Transbalkan corridor is fully in line with three basic goals of EU energy policy: increasing of security of supply, integration of renewable generation and establishing internal electric energy market accross Europe, and is acordingly recognised in ENTSO/E panEuropean TYNDP as well as in the appropriate Regional Investment Plan of ENTSO/E and supported by EC.
• The first investment item, 400 kV OHL Pancevo – Resica was marked by EC as a PCI (Project of common interest) and its realisation was monitored by EC.
• Energy Community marked all sections of Transbalkan corridor as projects of the highest regional interest within the process of building the PECI list (PECI Projects of Energy Comunity Interest).
• A special Law on establishing the public interest and the special procedures of the expropriation and obtain documentation for the realization of construction of electricity transmission 400 kV TransBalkan corridor has been prepared by Ministry of Mining and Energy and adopted by the RS parliament.
• Transbalkan corridor - Phase I envisages construction of approximately 350 km of 400 kV OHLs (of which almost 300 km is double circuits, and increase capacity of substations for about 1,500 MVA,
• The total estimated budget value of the first phase of construction of the project TransBalkan corridor is approximately 157 MEUR.
• The project will reduce congestion in the region and will allow the electricity market to develop, providing benefits to the generators / supply companies faciliating connection of new renewable energy sources.
• TSOs and societies in the Region of SEE will earn revenue from transit fees, and stronger electricity connections will result in reduced supply interruptions and better supply quality to electricity customers.
• Transmission system losses will be reduced leading to more efficient transmission and environmental benefits in CO2 emission reductions. System robustness and flexibility will be enhanced and socioeconomic welfare will be improved for all customer groups (Domestic, Commercial and Industrial) throughout the 3 countries and in the region as the energy market develops.
-
Basic project data
Descriptions |
Serbia |
Project promoter company/Organization full name |
AD Elektromreza Srbije (EMS)
|
Shareholders of the project promoter company
|
|
Project name
|
Double OHL 400 kV Obrenovac - Bajina Basta
|
Project PECI or PMI
|
PECI |
Project Code on the current (2020) PECI/PMI list
|
El_01 b |
Project Name on the current (2020) PECI/PMI list
|
New double circuit 400 kV OHL SS Obrenovac (RS) – SS Bajina Basta (RS) with upgrade of SS Bajina Basta (RS) to 400 kV |
Project Code on the current (2019) EU PCI list |
no |
Project Name on the current (2019) EU PCI list |
n/a |
Project final investment decision status |
FID |
Project Name in the ENTSO(G/E) TYNDP 2020 Submission |
227 - Transbalkan Corridor |
Project Code in the ENTSO(G/E) TYNDP 2020 Submission |
TYNDP2020 reference code 227 |
Project Name in National NDP /Infrastructure Plan |
ДВ 2х400 kV ТС Обреновац – ТС Бајина Башта, са подизањем напонског нивоа у ТС Бајина Башта на 400 kV |
Project Code in National NDP /Infrastructure Plan |
n/a
|
National NDP / Infrastructure plan publication year |
2020 |
National NDP/infrastructure plan publication website |
Transmission system development plan of the Republic of Serbia 2020-2029, October 2019 |
Project website according to Article 9(7) of Regulation (EU) 347/2013 |
Transbalkan Corridor for Electricity Transmission, EMS-website
|
Name/website of the designated competent authority in the country |
Ministry of Mining and Energy of the Republic of Serbia |
Address of the designated competent authority in the country |
22-26 Nemanjina St., 11000 Belgrade
|
-
Project details - technical information
Start point in country |
SS Obrenovac |
End point in country |
SS Bajina Basta |
Technical information |
Element type |
line
|
Investment type
|
new |
Line circuit type |
double circuit |
Voltage level value [kV] |
400 |
Capacity [MW] |
2x1000 |
Line length [km] |
109 |
Line current type |
AC |
Line structure type |
overhead line |
-
Project Implementation Plan Article 5(1)
Project Pre-feasibility Assessment |
Serbia |
Start: 2009, January |
End: 2010, March |
Details - Explanation |
Completed in March 2010. Adoption to the national legislative finished in December 2017. |
Percentage Done (%) |
100% |
Feasibility Assessment, ESIA/EIA and Design Studies |
Serbia |
Start: 2010, March |
End: 2011, September |
Details - Explanation |
Feasibility Study, Preliminary Design and Environmental Impact Assessment Study, funded by WBIF, were completed in 2011. However, due to incoherencies with the national legislation, KfW grant in amount of EUR 250,000 was received for adapting the studies to the national legislation, which was done in December 2017.
|
Percentage Done (%) |
100% |
FEED/Main Design |
Serbia |
Start: 2019, January |
End: 2021, September |
Details - Explanation |
KfW provided support in obtaining a WBIF grant of 0.8 MEUR for the development of the missing technical documentation (Design for Building Permit and Project execution plan). A consultant has been selected to develop the Terms of Reference (ToR) for the missing technical documentation. The ToR has been developed by the Consultant, and approved by KfW.
Technical documentation preparing started in May 2019. Up to May 2021, Design for construction permit for SS is completed, and Design for construction permit for OHL is nealr completion with the technical control being in progress.
|
Percentage Done (%) |
90% |
Market Survey - Open Season/Capacity Auction |
Serbia |
Start: |
End: |
Details - Explanation |
|
Percentage Done (%) |
|
Permitting |
Serbia |
Start: 2019, May |
End: 2021, September |
Details - Explanation |
Expected to start in Y2021. Construction permit for SS has been obtained in April 2021, and the request for Construction permit for OHL is expected in July 2021.
|
Percentage Done (%) |
70% |
Regulatory/Authority Approval of the project |
Serbia |
2017, December |
Details - Explanation |
According to the National Law, the competent authorities approve the JSC EMS' Development Plan and Investment Plan (where the project description is given). |
Final Investment Decision taken |
Serbia |
2020, December |
Details - Explanation |
After approval of the grant and signing of all necessary documents regarding financing, there are no more financial obstacles for the realisation of the project. |
Tendering |
Serbia |
Start: |
End: |
Details - Explanation |
Preparation of tender documentation will start after completion of final design and providing of construction permit. |
Percentage Done (%) |
|
Construction |
Serbia |
Start: 2021, November |
End: 2024, November |
Details - Explanation |
|
Commissioning |
Serbia |
2024, December |
Details - Explanation |
Dates are estimated providing the required amount of investment grant is approved by WBIF. |
-
Project Annual Report Article 5(4)
Project evolution since 2013 |
Serbia |
Evolution driver description |
Rescheduled
|
Explanation |
Financing delayed. Inadequate financial scheme offered by the WBIF and lead IFI to cover the negative financial NPV that JSC EMS have foreseen from this project. |
Mitigation measures to ensure project schedule |
Negotiation with WBIF and lead IFI regarding the amount of financial grant.Final agreement reached in 2021. |
Project implementation actions conducted since 2016 |
Serbia |
Project development |
Prefeasibility and Feasibility study were completed in 2011. KfW grant (0.25 MEUR) was approved to harmonize Feasibility study, Preliminary design and EIA to national legislation (done in December 2017). WBIF grant for technical assistance in the amount of 0.8 MEUR was approved (for the Design for construction permit and for project execution plan). A consultant has been selected to develop the Terms of Reference (ToR) for the missing technical documentation. The ToR has been developed by the Consultant and approved by KfW in November 2018. The consultant for developing the technical documentation has been selected. Initial meeting has been held in January 2019 and the work on the documentation has begun in May 2019.
Spatial Plan of the Special Purpose Area has been adopted by the Government of the Republic of Serbia in March 2020. Design for construction permit for SS and for OHL are finished. |
Permit Granting |
Expected in year 2021. |
Consultation procedures |
JSC EMS have had consultations and meetings with the following national institutions: Ministry of Mining and Energy of the Republic of Serbia, Ministry of Finance, Ministry of European Integration (former Serbian European Integration Office), and National Regulatory body – Energy Agency of Republic of Serbia (AERS).
In addition, JSC EMS conducted several meetings and consultations with EU Delegation in Republic of Serbia, European Commission Directorate-General for Neighbourhood and Enlargement Negotiations (DG NEAR) as well as representatives of IFIs (EBRD and KfW).
Other stakeholders, such as local municipalities, have also been contacted, and public hearings will be organized when the Spatial Plan of Special Purpose Area is presented. |
Construction |
Expected to start in Q1 2023 |
Commissioning |
Expected in Q4 2025 |
-
Project CAPEX and financing information
CAPEX Information |
Serbia |
Project CAPEX - total (mEUR) |
58,95 mEUR
|
Year 1 (till 2021) |
1,715 mEUR |
Year 2 (2021)
|
0,109 mEUR |
Year 3 (2022)
|
0,594 mEUR |
Year 4 (2023) |
22,847 mEUR |
Year 5 (after 2023) |
33,685 mEUR |
Project CAPEX SUM
|
|
Project CAPEX certainty (+/-%)
|
5% |
Has the project CAPEX estimate changed since PECI/PMI submission |
Yes. Land purchase was adjusted according to the most recent information. Also, upgrade of SS Valjevo to 400 kV level was excluded from the project. Thus, the project cost was reduced for about 7 mEUR. |
Financing Information |
Serbia |
Applied for IFI Financing (yes/no) |
yes
|
Granted (yes/no) |
yes |
Which institution and in what is the amount (mEUR)
|
KfW, 40 mEUR |
When |
February 2021 |
Applied for Grants from IPA/NIF (yes/no) |
yes |
Granted (yes/no) |
yes |
When |
2019, November |
What is the amount (mEUR) |
12,8 mEUR |
-
Additional project information
International Cooperation - International Agreement(s) signed |
Serbia |
When |
|
Signatories of the Agreement |
|
Short description |
|
Foreseen Regulatory Regime - Third Party Access |
Serbia |
Regulated Third Party Access |
no |
Negotiated Third Party Access |
no |
Exempted from Third Party Access capacity and duration (% of total and MW) |
no |
Barriers to Project Implementation |
Serbia |
Regulatory Framework |
no |
Permit Granting |
no |
Financing |
no |
Political |
no |
Market |
no |
Which incentives would support the realization of the project |
|
Final remarks, other |
The successful implementation of project depends on approved WBIF grant. Grant is approved, Loan and Grant agreements were signed as well as Separate agreement in December 2020. |