Case ECS-06/14: Montenegro / renewable energy

summary of the case

status: closed in preliminary procedure (Art.91) /
complied in preliminary procedure
registered: ex officio 2014

 


 

 


The Secretariat, acting under Article 90 of the Treaty, notes that five Contracting Parties, including Montenegro, have not adopted and submitted to the Secretariat a National Renewable Energy Action Plan. The deadline for adoption and notification to the Secretariat expired on 30 June 2013.

Case ECS-06/14 was closed on 15 January 2015 because of compliance after Opening Letter.